Details of Completed Projects


Each project below has been approved and this page includes a status update on its current progress. This page is updated monthly.


#021 Sullivan Elementary

  • Address:6016 152nd St., Surrey, B.C., V3S 3K6
  • Date of Approval: Ministry of Education approval received March 18, 2017
  • Current Phase: Construction - Construction contract awarded to Clark Builders
  • Current Size: 9 Classrooms
  • Project Type: Addition - 8 Classrooms
  • Final Size: 17 Classrooms
  • Target Occupancy: June 2021

#177 Grandview Heights Secondary

  • Address:16987 25th Ave.
  • Date of Approval: Ministry of Education revised budget approval received Dec. 6, 2018
  • Current Phase: Construction - Construction contract awarded to Yellowridge Construction Ltd.
  • Project Type: New Secondary School - 60 Classrooms
  • Target Occupancy: September 2021

#184 Maddaugh Elementary

  • Address:19405 76th Ave.
  • Date of Approval: Ministry of Education revised budget approval received Dec. 6, 2018
  • Current Phase: Construction
  • Tender: Construction contract awarded to Pro-Can Construction Group Corp.
  • Project Type: New Elementary School - 25 Classrooms
  • Target Occupancy: March 2021 (previous target date February 2021)

#157 Coyote Creek Elementary

  • Address:8131 156th St., Surrey, B.C., V3S 3R4
  • Date of Approval: Ministry of Education funding approval April 30, 2018
  • Current Phase: Construction - Construction contract awarded to Mierau Contractors Ltd.
  • Current Size: 26 Classrooms (including modular)
  • Project Type: Addition - 4 Classrooms
  • Final Size: 30 Classrooms (including modular)
  • Target Occupancy: February 2021