This translation tool is provided by Google Translate and offers a wide variety of languages. While the tool is intended to provide users with a basic translation of the information available on our website, it may lose some accuracy or context when translating into certain languages.Surrey Schools cannot guarantee the accuracy of any translated information and it is highly recommended that users contact the appropriate departments before acting upon translated information.
Start entering a first or last name to find someone.
[ Progress Chart | Project Details | Future Projects | Completed Projects ]
[ 2022-23 Five Year Capital Plan | Capital Plan Summary: English / Mandarin / Punjabi ]
A project is considered approved once funding has been committed from the Ministry of Education. Normally, there is an initial announcement by the Ministry of Education which is support to proceed to prepare a Project Definition Report (PDR). Any project on this list has received funding required for design and construction.
This Progress Chart is updated following each board meeting.
Following approval of the funding agreement with the Ministry of Education, the Design stage begins.
Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a detailed design. This detailed design is used to secure City of Surrey development/building permits and are part of the tender package.
When a project's design is complete, the project is put to tender. Construction companies bid on the contract to build new schools and expansions.
After the project has been awarded to the successful bidder, construction can begin.
This stage has many varying factors that can affect the length of time required to finish a project.
At the Target Occupancy stage, we furnish, fit and occupy the new development. While the building is now being used as planned, minor work continues.